prim33880:Can Check Project Integrity report and correct orphaned UDFVALUE...
Solution ID: prim33880 Can Check Project Integrity report and correct orphaned UDFVALUE records so XER can be successfully exported and imported without error? Status: Reviewed Version(s): 5.0 From...
View Articleprim34222:Can Past Period Actuals be Imported from one Project Management...
Solution ID: prim34222 Can Past Period Actuals be Imported from one Project Management database to another? Status: Reviewed Version(s): 5.0, 6.0, 6.1, 6.2 From Primavera OCP Problem: Can Past Period...
View Articleprim34287:How to make a Backup of a Project.
Solution ID: prim34287 How to make a Backup of a Project. Status: Reviewed Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1 From Primavera OCP Problem: How to make a Backup of a Project. Problem: Where...
View Articleprim34348:Can I update Role names in MethodologyManagement by importing an...
Solution ID: prim34348 Can I update Role names in Methodology Management by importing an XER with the updated values? Status: Reviewed Version(s): 5.0 From Primavera OCP Problem: Can I update Role...
View Articleprim34509:Asterisk appears in the dates column, although no constraints have...
Solution ID: prim34509 Asterisk appears in the dates column, although no constraints have been applied to the activity Status: Reviewed Version(s): 5.0, 6.0, 6.1, 6.2, 6.2.1, 7.0 From Primavera OCP...
View Articleprim34563:Why didn’t my project save?
Solution ID: prim34563 Why didn’t my project save? Status: Reviewed Version(s): 4.1 From Primavera OCP Problem: Why didn’t my project save? Problem: Project has reverted to a previous state Problem:...
View Articleprim34605:Error: “UCVFC-2820-4″ when importing an XER
Solution ID: prim34605 Error: "UCVFC-2820-4" when importing an XER Status: Reviewed Version(s): 4.0, 4.1, 5.0 From Primavera OCP Problem: Error: “UCVFC-2820-4″ when importing an XER Problem:...
View Articleprim34653:SQL Server Performance Issues in version 5.0
Solution ID: prim34653 SQL Server Performance Issues in version 5.0 Status: Reviewed Version(s): 5.0 From Primavera OCP Fact: SQL Server Performance Problem: SQL Server Performance Issues in version...
View Articleprim34702:Event Code VTDCF-3961-2 (Role rate count cannot exceed 1) when...
Solution ID: prim34702 Event Code VTDCF-3961-2 (Role rate count cannot exceed 1) when importing XER Status: Reviewed Version(s): 4.0, 4.0, 4.1, 4.1, 5.0 From Primavera OCP Problem: Event Code...
View Articleprim34738:Can the default EPS for “Import To” be changed during XER import?
Solution ID: prim34738 Can the default EPS for "Import To" be changed during XER import? Status: Reviewed Version(s): 4.1, 5.0 From Primavera OCP Problem: Can the default EPS for “Import To” be...
View Articleprim34845:Scheduling/Leveling options are carried over when a project is...
Solution ID: prim34845 Scheduling/Leveling options are carried over when a project is exported to XER, but revert back to default options when imported back to the database with Import option set to...
View Articleprim35118:How do I run a Global Change to set Planned Dates equal to...
Solution ID: prim35118 How do I run a Global Change to set Planned Dates equal to Start/Finish Dates? Status: Reviewed Version(s): 4.1, 5.0 From Primavera OCP Problem: How do I run a Global Change to...
View Articleprim35169:Canyou select a currency when importing from P3?
Solution ID: prim35169 Can you select a currency when importing from P3? Status: Reviewed Version(s): 5.0 From Primavera OCP Problem: Can you select a currency when importing from P3? Problem: Costs...
View Articleprim35283:Why does importing an XER into Project Management from a Data Key /...
Solution ID: prim35283 Why does importing an XER into Project Management from a Data Key / Stick sometimes fail? Status: Reviewed Version(s): 4.0, 4.1, 5.0 From Primavera OCP Problem: Why does...
View Articleprim35571:When exporting project data to XER, MPP, MPX or XLS, can all...
Solution ID: prim35571 When exporting project data to XER, MPP, MPX or XLS, can all projects be easily unchecked in the ‘Projects to Export’ window? Status: Reviewed Version(s): 4.1, 5.0 From...
View Articleprim35592:Can a version 2.0 XER be imported into Project Management 5.0?
Solution ID: prim35592 Can a version 2.0 XER be imported into Project Management 5.0? Status: Reviewed Version(s): 5.0 From Primavera OCP Problem: Can a version 2.0 XER be imported into Project...
View Articleprim35782:When using P330XERConvert.exe, an error messageappears that the...
Solution ID: prim35782 When using P330XERConvert.exe, an error message appears that the file cannot be found. Status: Reviewed Version(s): 4.1, 5.0 From Primavera OCP Problem: When using...
View Articleprim35890:When importing an XER file what import actions are available
Solution ID: prim35890 When importing an XER file what import actions are available Status: Reviewed Version(s): 5.0, 6.0, 6.1 From Primavera OCP Problem: What Import Action do I chose when importing...
View Articleprim36825:Activity code values are duplicated after importing an XER file
Solution ID: prim36825 Activity code values are duplicated after importing an XER file Status: Reviewed Version(s): 4.1, 5.0 From Primavera OCP Fact: The XER file is imported into a database or...
View Articleprim36861:Why is Budgeted Cost not linking to Units after importing a project...
Solution ID: prim36861 Why is Budgeted Cost not linking to Units after importing a project from P3? Status: Reviewed Version(s): 4.1, 5.0 From Primavera OCP Problem: Why is Budgeted Cost not linking...
View Article