Solution ID: prim11979 |
Can Project Manager import more than one *.xer file at a time? |
Status: Reviewed |
Version(s): 3.5.1, 4.0, 4.1 |
Problem: | Can Project Manager import more than one *.xer file at a time? |
Fix: | At this time Project Manager can only import one *.xer file at a time. It is possible to import multiple projects at one time because an *.xer file can contain multiple projects. If multiple projects are open and selected for Export, all of the selected projects will be exported to a single *.xer file. |