Solution ID: prim18450 |
Can Project Manager/Management export the Project’s Baselines to an XER file? |
Status: Reviewed |
Version(s): 3.x, 4.0, 4.1, 5.0, 6.0, 6.1, 6.2, 6.2.1 |
From Primavera OCP
Problem: | Can Project Manager/Management export the Project’s Baselines to an XER file? |
Problem: | When Exporting to .mpp format, Baseline doesn’t come over either. |
Fix: | This issue is an existing Enhancement Request. Workaround: To export the Baselines, restore them as Projects in their own right and Export them to the same XER file (or in separate XER files, for Contractor). Once the XER(s) have then been imported (to Contractor, or the full Primavera suite) then the baselines can be added back to the main project using the “Convert another project to a new baseline of the current project” option from the Project, Baselines menu option. |