Solution ID: prim19428 |
Error: "Event Code: GSQLE-2099-0: value larger than specified precision allows for this column" when importing a Project Management XER file into Methodology Management |
Status: Reviewed |
Version(s): 3.x, 4.0, 4.1 |
From Primavera OCP
Problem: | Error: “Event Code GSQLE-2099-0: value larger than specified precision allows for this column” when importing a Project Management XER file into Methodology Management |
Cause: | This error is caused by a large amount of resource data in the project and by choosing the ‘Use Actuals’ (project’s actual historical data) option instead of ‘Use Planned Values’ (project’s planned effort and cost values). |
Fix: | This known problem will be corrected in a future release. Workaround: Copy the project in Project Management and run a Global change to set the Planned\Budgeted Units and Cost to the At Completion Units and Cost. Create the XER and import that XER into Methodology Management choosing Planned instead of Actuals. |