Solution ID: prim29842 |
How are Global Activity Codes handled when a project is exported and imported into a different Project Management database? |
Status: Reviewed |
Version(s): 4.0, 4.1, 5.0, 6.0, 6.1, 6.2 |
From Primavera OCP
Problem: | How are Global Activity Codes handled when a project is exported and imported into a different Project Management database? |
Problem: | How are Project Activity Codes handled when a project is exported and imported into a different Project Management database? |
Problem: | Are all Global activity codes exported in an XER? |
Problem: | Activity Code values are missing when I import a project. |
Problem: | Activity Codes are missing when I import a project. |
Fix: | When a project is exported as an XER file, the only Global Activity Code data that is exported is the data that is assigned to activities in the project being exported. Thus, only codes that have values assigned are exported, and only values that are assigned for those codes are exported. To illustrate this, please do the following:
|
Fix: | When a project is exported as an XER file, all Project Activity Code data is exported, regardless of whether any values are assigned to activities in the project being exported. |